To view the Actuals Summary report, perform any of the following actions.

  • View the report in the Actuals screen:

    1. Navigate to Progress > Actuals.

    2. Click the Reports tab.

    3. Click the Actuals Summary hyperlink. A dialog box appears with a title Project Actuals Summary.

    4. Click the Project ellipses to select the required project. By default, the last selected project appears.

    5. Click the Run button. The preview of the report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Actuals > Actuals Summary.

    2. Click the Project ellipses to select the required project. By default, the last selected project appears.

    3. Click the Run button. The preview of the report appears.