View Assigned Resources for Project Schedule Activity - EcoSys - 3.01 - Help - Hexagon PPM

EcoSys Projects Help (3.01)

PPMProduct
EcoSys
PPMCategory_custom
Help
Version_EcoSysStand
3.01

This procedure allows you to view the resources assigned for the selected activity in the project schedule activity.

  1. Click the Baseline tab.

  2. In the Activity Scheduler Baseline panel, select the activity row for which you want to view the assigned resources.

  3. Click the Resource Assignments - Baseline tab.

    You can customize the view of the Resource Assignments - Baseline spreadsheet from the view settings.