Generate Project Quantity Progress Details Report - EcoSys - 3.01 - Help - Hexagon PPM

EcoSys Projects Help (3.01)

PPMProduct
EcoSys
PPMCategory_custom
Help
Version_EcoSysStand
3.01

To view the Project Quantity Progress Details report, perform any of the following actions.

  • View the report in the Earned Value screen:

    1. Navigate to Progress > Earned Value.

    2. Click the Reports tab.

    3. Click the Project Quantity Progress Details hyperlink. A dialog box appears with a title Project Quantity Progress Details.

    4. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    5. Click the Run button. The preview of the report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Earned Value > Project Quantity Progress Details.

    2. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    3. Click the Run button. The preview of the report appears.