Generate Project Budget Details by CBS Report - EcoSys - 3.01 - Help - Hexagon PPM

EcoSys Projects Help (3.01)

PPMProduct
EcoSys
PPMCategory_custom
Help
Version_EcoSysStand
3.01

To view the Project Budget Details by CBS report, perform any of the following actions.

  • View the report in the Original Budget screen.

    1. Navigate to Budgets > Original Budget.

    2. Click the Reports tab.

    3. Click the Project Budget Details by CBS hyperlink. A dialog box appears with a title Project Budget Details by CBS.

    4. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    5. Click the Run button. The preview of the report appears.

  • View the report in the Current Budget screen.

    1. Navigate to Budgets > Current Budget.

    2. Click the Reports tab.

    3. Click the Project Budget Details by CBS hyperlink. A dialog box appears with a title Project Budget Details by CBS.

    4. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    5. Click the Run button. The preview of the report appears.

  • View the report from the Reports menu.

    1. Navigate to Reports > Budgets > Project Budget Details by CBS.

    2. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    3. Click the Run button. The preview of the report appears.