This procedure allows you to establish the project structure-specific currency and rate tables.

  1. In the Project Structure Details panel, click the Currency & Rates tab.

  2. Click the Object Currency ellipsis to select the object currency for the project structure. By default, US Dollar appears.

  3. Click the Object Exchange Rate Table ellipsis to select the required object exchange rate table for the project structure.

  4. Click the Object Hours Rate Table ellipsis to select the required object hours rate table for the project structure.

  5. Click the Object Quantity Rate Table ellipsis to select the required object quantity rate table for the project structure

  6. Click SAVE.