This procedure allows you to establish adjustments for the project estimates. You can either create new adjustments from the Summary Adjustments hyperlink in the Estimate Summary panel or add the adjustments to the line items of each project cost accounts (Labor, Material, Equipment, and ODC) in the Line Item Adjustment tab.

You must always do the adjustments in the Line Item Adjustment tab, prior to creating any new adjustments from the Summary Adjustments hyperlink in the Estimate Summary panel

  1. Navigate to Estimating > Estimate Summary.

  2. At the top of the screen, in the green parameter bar, click the Project ellipsis to view all the estimate details.

  3. Click Refresh for screen update.

  4. Click the Estimate Summary tab. The Estimate Summary panel appears.