This procedure allows you to add work steps and calculate the weighted % complete for a particular activity.
-
In the Activity Scheduler panel, select the row for which you want to add work steps.
-
In the Activity Task Scheduler Tabs panel, click the Work Steps tab.
-
Click the Insert Row icon to add a new row for a work step.
-
Type in the below fields:
-
ID - Type a work ID.
-
Description - Type the description of the work.
-
Weight - Type the weightage out of 100% for the particular work step.
-
-
% Complete - Type the percentage of the work completed for the particular work step.
-
Click SAVE. The fields Activity and Weighted % Complete auto-populate.
-
Progress Form must have Actual Start Date populated and Progress Type set to Percent Complete for the Weighted Steps to write to the Progress of the schedule WBS activity.
-
Click the Delete Row(s) icon to delete the selected row.
-