View or Establish Schedule Structure - EcoSys - 3.01 - Help - Hexagon PPM

EcoSys Projects Help (3.01)

PPMProduct
EcoSys
PPMCategory_custom
Help
Version_EcoSysStand
3.01

Follow the procedure below to setup a Schedule WBS Activity.

  1. Navigate to Scheduling > Project Schedules.

  2. In the Project Schedule Register panel, select the required Project ID hyperlink against the Schedule WBS Activity scheduler method.

  3. (Optional) To change the project within the same scheduler method, in the Schedule WBS Module panel, at the top of the screen, in the green parameter bar, click the Project ellipsis and select the required project.

  4. If required, click REFRESH to update the screen.