This procedure allows you to update the Manual EAC amount manually for cost control objects with a Manual EAC forecasting method.
When the Manual EAC forecasting method is selected, the background color of the Manual EAC column turns green.
-
Navigate to Forecasts > Forecast.
-
Click the Forecast tab.
-
In the Project Forecast Summary panel, type in the Manual EAC for the cost control objects with Manual EAC forecast method.
-
Click the Save icon.