To view the Project Forecast Details by CBS report, perform any of the following actions.

  • View the report in the Forecast screen:

    1. Navigate to Forecasts > Forecast.

    2. Click the Reports tab.

    3. Click the Project Forecast Details by CBS hyperlink. A dialog box appears with a title Project Forecast Details by CBS.

    4. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    5. Click the Run button. The preview of the report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Forecasts > Project Forecast Details by CBS.

    2. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    3. Click the Run button. The preview of the report appears.