This procedure allows you to update the Manual ETC amount manually for the projects with a Manual EAC forecasting method.

Manual ETC must be updated whenever the forecasting cycle first begins for the project and after the previous forecast variance change has been approved, a new forecast cycle for a new project period begins.

When the Manual ETC forecasting method is selected, the background color of the Manual ETC column turns green.

  1. Navigate to Forecasts > Multi Project Forecast.

  2. Type in the Manual ETC for the projects with Manual ETC forecast method.

  3. Click the Save icon.