This procedure allows you to update the project material rates.

  1. Click the Rate Tables tab.

  2. In the Rates panel, click Update Project Material Rates.

  3. Click the Insert Row icon to add a new labor rate.

  4. Click the Material ID ellipsis to select the required material.

  5. Click the Currency ellipsis to select the currency.

  6. Click the Transaction Category: Region ellipsis to select the required region.

  7. Type in the required Rate: Base.

  8. Click SAVE. The Material Name auto-populates based on the Material ID selected.

    Click the Delete Row(s) icon to delete the material rate.