If there are documents you are interested in that were not automatically assigned to you, you can register your interest in reviewing a document by selecting each type of document issue purpose you require, such as Issued for Design. Each time the document is revised or changed, you are informed that the document requires a review.
The following table lists the standard set of issue purposes.
Icon |
Name |
Description |
---|---|---|
Prelim |
Preliminary |
The document is issued as the first preliminary draft. |
IFR |
Issued for Review |
The document has been issued for review. |
IFD |
Issued for Design |
The document is a project design document. |
IFC |
Issued for Construction |
The document has been issued for a construction project. |
AB |
Issued for As-Built |
The document has been issued for the accepted as-built project. |
Final |
Issued for Final |
The document has been issued as the final document revision. |
Click Expand to display the issue purpose details, including any rules applied to that issue purpose.
You can configure additional issue purposes, see Configure issue purposes.