Smart Electrical allows you to perform bus and PDB load summaries based on various sets of load values. These various sets of load data (referred here to as plant operating cases) provide the ability to analyze the total electrical load consumption of your plant based on different load properties and values. Typically, such operating cases are called Winter, Summer, and so on. However, you can create and define a number of such operating cases which cover your plant requirements.
Operating cases are defined in Options Manager. See Manage Operating Case Data for Plant Items.
This dialog enables you, in one single operation, to switch all the plant loads, instruments and cabinets to a plant operating case that you select.
Operating Case
Displays the name of the operating case. Select the option button to the left of the name to select it as the active case.
Description
Displays the description of the operating case.
Switch
Select to make the switch to the selected operating case.