Click Work Packages on the project home page.
-
Select an IWP from the Work Packages browser.
-
Click Components on the open IWP to view components.
-
Click the Complete option to mark all work steps and components as complete for an IWP.
-
If progress has been reported for a component or a work step, man hours and other details for the component or the work step cannot be modified.
-
You cannot add labor adjustment factors to an IWP or a work step with progress reported.
-
You cannot move components or work steps from one IWP to another if progress is reported. To move the component or work step, clear the progress, then drag the component or work step to the target IWP.