You can view the components' rollup information, grouped by the cost code, and use this to manage your construction project better.
The cost codes are associated to the components assigned to the IWP under all the CWPs for this CWA.
Click Refresh to view the latest information on the summary window.
Value |
How the value is calculated |
---|---|
Forecasted Man Hours |
(Sum of the units of components using the cost code in the CWA) x (Cost code rate) First, add the units of components that use the same cost code in the CWA, and then multiply that number by the cost code rate. The units of components is the amount or quantity of component required. The cost code rate is the number of man hours needed to complete one unit of measure (UoM) of work for a specific work step type. |
Planned Man Hours |
The sum of planned man hours of components using the same cost code that are packaged in any IWP in the CWA. |
Completed Man Hours |
The sum of completed man hours of the components using the same cost code that are packaged in any IWP in the CWA. |