Changing units of a progressed component causes an inconsistency in the IWP component's completed man-hours - Intergraph Smart Construction - Hotfix 14 - Help - Hexagon

Intergraph Smart Construction Help

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
8
SmartPlant Foundation / SDx Version
10

Problem

When the user changes the units of a progressed component, the completed man-hours shown in the IWP Components tab are incorrect.

Solution

In the Work Packages tab, right-click the IWP which has the affected component, and click Recalculate Man Hours.

For users to access the Recalculate Man Hours menu option, an administrator must assign the user's access group to the RecalculateIWPManHours method in the SmartPlant Foundation Desktop Client.