Other cost for addenda costs.
When creating an agreement based on a quote or when adding a quote to an agreement, the addenda costs (if applicable) are captured by creating one other cost for them.
With this project default, you define the name of the other cost that is to be used for this purpose.
If addenda costs exist and this project default is not set, you cannot create or enlarge the agreement.
-
Module(s) affected by this setting: P3001, P5001, P5007
-
Default value: ./.
-
List of Values: P1033 Other Costs