On this tab, you can maintain SOW milestones and their details attached to the agreement.

This tab is only available for subcontracting agreements.

You can select the date of the start activity from the LOV in the Start Work field.

Select the name (code) of the start activity from the LOV in the Start Activity field. Activities are defined on the J.30.01 Activities screen. You can call this screen by double-clicking in this field.

You can select the date of the substantial activity from the LOV in the Substantial Completion field.

Select the name (code) of the substantial activity from the LOV in the Substantial Activity field. Substantial activities are defined on the J.30.01 Activities screen. You can call this screen by double-clicking in this field.

You can select the date of the final activity from the LOV in the Final Completion field.

Select the name (code) of the final activity from the LOV in the Final Activity field. Final activities are defined on the J.30.01 Activities screen. You can call this screen by double-clicking in this field.

In the Interim Milestones block, you can maintain SOW milestone details (interim milestones) attached to the agreement.

The Seq field displays the order sequence of the interim milestones.

The description of the interim milestone is shown in the Interim Milestone field.

Select the name (code) of the activity assigned to the interim milestone from the LOV in the Activity Code field. Activities are maintained on the J.30.01 Activities screen. You can call this screen by double-clicking in this field.

You can select the date of the activity from the LOV in the Date field.