In addition to MSCM-specific project defaults (that are also relevant when using the OPI interface), the setting of the ZI_OPI_COM project default is very important.

  • This project default determines the level where commits are performed during the OPI import.

  • If you set this project default to RECORD, a commit is done after each record that can be processed successfully.

  • Once an error has been encountered the processing for an order stops even if the commit level is set to RECORD. For example, if the second order line item contains any errors, all subsequent order line items will not be processed.

  • If the project default is set to ORDER, a commit is done after each order after all its details have been processed successfully.

You can open the A.60.63 Valid Settings screen via the toolbar on the OPI 10.01 screen to see the full and actual list of settings needed for OPI.

For more information see Project Defaults.