Select the Impacts tab.
-
Click Add Impact.
-
If you report a cost impact, do the following:
-
Type the cost value in the Amount cell.
-
Select a currency from the list in the Currency cell.
-
Type a comment in the Cost Comment box on the Comments tab.
-
-
If you report a schedule impact, do the following:
-
Type the number of delay days in the Calendar Days box.
-
Type a comment in the Schedule Comment box on the Comments tab.
-
-
If you report a drawing impact, do the following:
-
Select the Update Required check box.
-
Type a comment in the Drawing Comment box on the Comments tab.
-
-
Click Send.