Edit item progress details - Intergraph Smart Materials - 10.2 - Help - Hexagon

Intergraph Smart Materials Portal Help

Language
English
Product
Intergraph Smart Materials
Subproduct
Portal
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.2

To track the period progress, you must edit the detail information.

  1. Click the respective Agreement Number on the Subcontracting dashboard to open the Progress and Payment - Item Progress page.

  2. Select a period progress number that is not submitted, then in select the Details tab and click Add Item .

  3. Select all item shipments you want to add to the period progress and then click Add.

  4. To record the period progress, do one of the following:

    1. Type the value that has been completed in this period in the Period Progress Value cell. The period progress quantity and the period progress % are calculated.

    2. Type the quantity that has been completed in this period in the Period Progress Quantity cell. The period progress value and the period progress % are calculated.

    3. Alternatively, type the progress percentage value in the Period Progress % cell. The period progress value and the period progress quantity are calculated.

  5. Optionally, select an account code from the select list in the Account Code cell and click Save.

SHARED Tip To delete an item, select the item and click Delete Item .