This procedure allows you to update the adjustment methods in the Forecast Balance and Adjustment dialog box in the Forecast Time-Phasing panel.
If Time-Phase Settings adjustment method is assigned, then do not select Time-Phasing Method as Manual for that cost control object.
-
Navigate to Forecasts > Forecast.
-
Click the Time-phasing tab.
-
Click the New EAC hyperlink for a required cost control object.
-
For CCL objects:
-
Click the Forecast Adjustment Method ellipsis and select the required adjustment method. The available adjustment methods are listed below:
Adjustment to Time-Phasing End
Adjustment to Next
Adjustment to Future Periods
Adjustment to Year End
-
Type the number of Adjustment Periods for the cost control object with Adjustment to Future Periods adjustment method.
-
Click SAVE. The Adjustment ETC End Date gets updated.
-
Click the Refresh Forecast Adjustment hyperlink and then click OK.
The bar chart is updated and displays the adjustment amount distributed as per the adjustment method selected.
-
-
For Non-CCL objects, click Refresh Forecast Adjustment hyperlink and then click OK.
The bar chart gets updated and adjusts all the children of WBS.
-