This procedure allows you to add and schedule a new cost object to a project in the Project Scheduler tab.

  1. Click the PROJECT SCHEDULER tab.

  2. In the Project Scheduler panel, select the row below which you want to add a new cost object and click the Add New Row Add New Row - Icon - Project Scheduling_4.11 icon.

  3. Click the Object ellipsis and select the cost object to which you want to add a project.

  4. Type a unique ID and Name.

  5. Click the Object Type ellipsis and select the cost object type.

  6. (Optional) Click Cost Control Level (ID) ellipsis and select Yes.

  7. (Optional) Type the number of hours/days in the Duration box and select the Duration Units accordingly.

    By default, the Duration Units are Hours.

  8. Click SAVE.

    You cannot delete any Object rows in this screen.

  9. Double-click the Start Date column.

    1. Select the Start Constraint Type from the list.

      If you do not select constraint type, EcoSys selects None as the constraint type.

    2. Click the Start Constraint Date ellipsis, select a start date and then click OK.

  10. Double-click the End Date column.

    1. Select the Finish Constraint Type from the list.

    2. Click the Finish Constraint Date ellipsis, select an end date and then click OK.

  11. If you have not selected the Duration while creating a new cost object, type the number of hours/days in the Duration column. Also, select the Duration Unit located above the Gantt chart.

  12. Click SCHEDULE.

    • If you do not run the Scheduler after making the changes to the chart, a yellow banner appears indicating that you must click SCHEDULE to execute the changes.

      Project Scheduler - Schedule button & Acknowledge_4.01

      Once you click the Acknowledge hyperlink on the banner, it disappears immediately. This yellow banner will no longer appear when scheduling is needed, instead a yellow triangle appears next to the SCHEDULE button on the top.

    • After making any changes, if you navigate away from the chart with unscheduled changes, a pop-up appears indicating that you have unsaved changes. Click OK to proceed.

    • Color codes for bar:

      • Red color bar indicates the cost object with longest duration and critical path.

      • Green color bar indicates non-critical path with float.

      • Blue color bar indicates progress of an cost object.

      • Gray color indicates the cost object that is yet to be scheduled.

        SHARED Tip

    • You can also view the cost objects, cost object attributes, and milestones of the project in the Gantt chart based on the timescale by selecting Show Subscale and the required timescale from the Timescale Subunit list. If the Timescale Unit is Day, you can no longer select Timescale Subunit.

      Scheduling - Project Schedules - Project Schedule - Project Scheduler panel_4.11