The estimate details are updated based on the rate source selected. The available rate source options are listed below:

  • Cost Object Unit Rate Table

  • None

  • Transaction Rate

  • Transactions Unit Rate Table

Follow the procedure below to view or update the estimate details.

You can add the estimate details to only those line items whose Cost Control Level is set to Yes in the Estimate Summary panel.

  1. Navigate to Estimating > Estimate Summary.

  2. At the top of the screen, in the parameter bar, click the Project ellipsis to view all the estimate details.

  3. Click the Refresh icon to update the screen.

  4. Click the ESTIMATE SUMMARY tab.

  5. In the Estimate Summary panel, click the Total Cost hyperlink. The bottom panel appears where the estimate details can be updated.

  6. Click the SUMMARY tab to view the summary of the project.

    You can customize the view of the Estimate Summary panel from the View Settings.

    Project estimate summary_4.11