This process allows you to view the productivity cost parameters and related charts.
-
Navigate to Progress > Productivity Analysis.
-
At the top of the screen, in the toolbar:
-
Click the Project ellipsis to select the required project.
-
Click the Project Period ellipsis to select the required project period.
-
Click the Chart Start Period ellipsis to select the required start date in the chart.
-
Click the Chart End Period ellipsis to select the required end date in the chart.
-
-
If required, click the Refresh icon to update the screen.
-
Click the Productivity Cost tab. The productivity analysis costs appear in the Productivity Analysis panel.
The below listed details appear in the Productivity Analysis panel:
-
Path ID - Displays the path ID of the object.
-
Name - Displays the name of the of the object.
-
BAC Cost - Displays the budget at completion value of the object.
-
PV Cost - Displays the present value cost of the object.
-
% Complete - Displays the percentage complete of the object.
-
EV AC Cost - Displays the sum of estimated actuals costs and actuals costs of the object.
-
EV Cost - Displays the earned value cost of the object.
-
EV CostR - EV CostR is equal to roll up cost of the earned value production cost.
-
CPI Cost - Displays the cost performance index value of the object.
-
SPI Cost - Displays the schedule performance index value of the object.
-
TCPI Cost - Displays to complete performance index value of the object.
-
TSPI Cost - Displays to complete schedule performance indicator value of the object.
-
Cost Variance - Displays the cost variance of the object.
-
Schedule Variance - Displays the schedule variance of the object.
-
IEAC1 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is BAC/CPI.
-
IEAC2 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is AC + (BAC – EV/ (CPI*.8) + (SPU*.2).
-
IEAC3 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is AC + (BAC-EV/CPI*SPI).
-
IEAC4 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is AC + (BAC-EV).
-
IEAC5 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is AC + EV + (BAC-EV)/CPIx.
-
-
(Optional) Type in a relevant Progress Comment.
-
To view the charts related to productivity costs,
-
View the project performance cost chart in the Project Performance Chart panel. The BAC (Budget At Completion), EV AC (Earned Value Actuals), and EV (Earned Value) values appear in a bar chart format.
-
To view the performance variance chart or performance factor chart for specific object, perform any of the following:
-
Click the CPI Cost hyperlink. The CPI and SPI costs specific to the object appear in a bar chart format.
-
Click the Cost Variance hyperlink. The cost variance and schedule variance specific to the object appear in a bar chart format.
-
-