View Productivity Cost Analysis - EcoSys - 4.03 - Help - Hexagon

EcoSys Projects Help (4.03)

Language
English
Product
EcoSys
Subproduct
Project
Search by Category
Help
EcoSys Standard Version
4.03

This process allows you to view the productivity cost parameters and related charts.

  1. Navigate to Progress > Productivity Analysis.

  2. At the top of the screen, in the toolbar:

    1. Click the Project ellipsis to select the required project.

    2. Click the Project Period ellipsis to select the required project period.

    3. Click the Chart Start Period ellipsis to select the required start date in the chart.

    4. Click the Chart End Period ellipsis to select the required end date in the chart.

  3. If required, click the Refresh icon to update the screen.

  4. Click the Productivity Cost tab. The productivity analysis costs appear in the Productivity Analysis panel.

    The below listed details appear in the Productivity Analysis panel:

    • Path ID - Displays the path ID of the object.

    • Name - Displays the name of the of the object.

    • BAC Cost - Displays the budget at completion value of the object.

    • PV Cost - Displays the present value cost of the object.

    • % Complete - Displays the percentage complete of the object.

    • EV AC Cost - Displays the sum of estimated actuals costs and actuals costs of the object.

    • EV Cost - Displays the earned value cost of the object.

    • EV CostR - EV CostR is equal to roll up cost of the earned value production cost.

    • CPI Cost - Displays the cost performance index value of the object.

    • SPI Cost - Displays the schedule performance index value of the object.

    • TCPI Cost - Displays to complete performance index value of the object.

    • TSPI Cost - Displays to complete schedule performance indicator value of the object.

    • Cost Variance - Displays the cost variance of the object.

    • Schedule Variance - Displays the schedule variance of the object.

    • IEAC1 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is BAC/CPI.

    • IEAC2 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is AC + (BAC – EV/ (CPI*.8) + (SPU*.2).

    • IEAC3 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is AC + (BAC-EV/CPI*SPI).

    • IEAC4 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is AC + (BAC-EV).

    • IEAC5 Cost - Displays the independent estimate at completion of the object. The formula used to calculate is AC + EV + (BAC-EV)/CPIx.

  5. (Optional) Type in a relevant Progress Comment.

  6. To view the charts related to productivity costs,

    1. View the project performance cost chart in the Project Performance Chart panel. The BAC (Budget At Completion), EV AC (Earned Value Actuals), and EV (Earned Value) values appear in a bar chart format.

    2. To view the performance variance chart or performance factor chart for specific object, perform any of the following:

      • Click the CPI Cost hyperlink. The CPI and SPI costs specific to the object appear in a bar chart format.

      • Click the Cost Variance hyperlink. The cost variance and schedule variance specific to the object appear in a bar chart format.