Resource Look Ahead is the resource utilization coming up in a selected time frame.

This process allows you to view the resource utilization hours coming up in the selected start and end week.

  1. Navigate to Projects > Project Manager Dashboard.

  2. At the top of the screen, in the toolbar:

    1. Click the Project ellipsis and select the required project.

    2. Click the Project Period ellipsis and select the required project period.

  3. Click the Resource tab.

  4. In the Resource Look Ahead panel, click the Start Week ellipsis and select the required date from the same month that is selected in the Project Period.

    By default, the Start Week auto-populates with a date from the same month that is selected in the Project Period.

  5. Click the End Week ellipsis and select the required end week date up to which you want to find the upcoming resource utilization hours.

  6. If required, click the Refresh icon to update the screen.