Manually Establish Forecasting Methods - EcoSys - 4.03 - Help - Hexagon

EcoSys Projects Help (4.03)

Language
English
Product
EcoSys
Subproduct
Project
Search by Category
Help
EcoSys Standard Version
4.03

This procedure allows you to establish a forecast method manually for each cost control object. If an object has a Cost Control Level assignment, the Forecast Method column will appear in yellow background. If a forecast method is not assigned, the Forecast Method will default to Current Forecast.

  • When the Forecast Method is modified, run the Refresh Time-Phased Forecast action.

  • For Contingency line items, the Forecast Method is set to read-only after running the Refresh Time-Phased Forecast action.

  1. Navigate to Forecasts > Forecast.

  2. Click the Forecast tab.

  3. Click the Forecast Method ellipsis to select the required forecast method. The available forecast methods are listed below:

    • AC + Open Commitment

    • Current Budget

    • Current CPI

    • Current Forecast

    • Greater of EAC or AC

    • Manual Details

    • Manual EAC

    • Manual ETC

    • Manual Factor

    • P6 Forecast Cost

    • Project Default

    • Schedule

    • Time Phased Forecast

      By default, the Forecast Method is selected as Current Budget for Contingency line items. This is a read-only attribute for Contingency line items.

  4. Click SAVE.

    The columns that contain data used to generate the forecast appears in a green background.

    forecast_4.03