This procedure changes the status of an Issue to Closed. Closed issues can no longer be edited. Once the issue is closed, a log entry appears, and all the workflow users established in the Project Setup screen with a Distribution List value set to All Workflows are notified.

  1. Navigate to Changes > Issues.

  2. Click the Actions list and select Close Issue.

  3. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    The Project displayed in the toolbar at the top of the screen is the only project available for selection in the Close Issue dialog.

  4. Click the Issue ellipsis to select the required issue. By default, the last selected issue appears.

  5. Select the Close Date.

  6. (Optional) Type the Comment.

  7. Click RUN and then OK. In the Issue Register panel, the status of the issue has changed to Closed.