This process allows you to create baselines for project schedule activity.
-
Click the BASELINE tab.
-
Click the Actions list and select Create Baseline.
-
Click the ellipsis for each of the below fields and select the required values:
-
Project - Select the project for which you want to create baseline.
The project selected in the tool bar at the top of the screen is the only project available to select.
-
Baseline - Select the required baseline.
-
-
(Optional) Comment - Type a comment related to the Baseline.
-
Click RUN and then OK.
Baselines appears under the project activity bars. They are indicated with tan color bars.