A defined set of time-phase methods can be used to establish the Curve, Start Date, and End Date. Once established, these attributes will be utilized when time-phasing the estimate project. The following time-phasing methods can be assigned:

  • Back Loaded - Line items spread in a back-loaded curve.

  • Front Loaded - Line items spread in a front-loaded curve.

  • Linear - Line items spread linearly.

  • Bell - Line items spread in a bell curve.

  1. Navigate to Estimating > Estimate Summary.

  2. At the top of the screen, in the toolbar, click the Project ellipsis to view all the estimate details.

  3. Click the Refresh icon to update the screen.