This procedure allows you to view and update the general schedule details of each activity.
-
In the Activity Scheduler panel, select the activity row for which you want to update general attributes.
-
In the Activity Task Scheduler Tabs panel, click the GENERAL tab.
-
Type the required Activity ID and Activity Name.
-
Type the number of hours/days required for the activity in the Duration field.
-
Select the units from the Duration Units list.
-
Type the Objective of the activity.
-
Click the Activity Calendar ellipsis and select the calendar for the activity.
External fields will be populated by the P6 Integration.