Thisrocedure allows you to assign resources and update all the details related to the activity.
-
In the Activity Scheduler panel, select the activity row for which you want to add or assign resources.
-
In the Activity Task Scheduler Tabs panel, click the RESOURCE ASSIGNMENT & RATES tab.
-
In the Resource Assignments panel, add new resources. There are two methods to add resources.
Manual - In the Resource Assignments panel, click the Insert Row icon to add a new row.
(Or)
Resource Rate Table - In the Resource Rates panel, click the Add hyperlink against the required resource.
The Resource ID and resource Rate are predefined in the Resource Rate table.
-
Click the ellipsis for each of the below boxes and select the required values.
-
Object Path ID (SBS/WBS) - Select the main object path ID.
-
Activity Path ID - Select the activity for which you want to assign resource.
-
Cost Account ID - Select the cost account ID
-
Resource ID - Select the resource ID that you want to assign
-
-
Type the values for the below attributes:
-
Description
-
Quantity
-
Hours
-
Rate (Hrs)
-
Cost
Rate attribute updates only when Hours are entered or changed.
-
-
Click the ellipsis for each of the boxes below and select the required values:
-
Curve - Select the appropriate curve
-
UOM - Select the required unit of measurement
-
Currency - Select the required currency
-
-
Click the Rate Source list and select the rate source.
-
Click SAVE. The Cost in Object Currency auto-populates.
Click the Delete Row(s) icon to delete the selected row.