This procedure allows you to update the balance methods in the Forecast tab.
If Time-Phase Settings balance method is assigned, then do not select Time-Phasing Method as Manual for that cost control object.
-
Navigate to Forecasts > Forecast.
-
Click the Forecast tab.
-
Click the Balance Method ellipsis to select the required forecast method. The available balance methods are listed below:
-
Balance to Time-Phasing End
-
Balance to Next
-
Balance to Future Periods
-
Balance to Year End
-
-
Type the number of Balance Periods for the cost control object with Balance to Future Periods balance method.
-
Click the Save icon.