The ABS project-specific header is used when an individual project’s project structure is subject to a unique reporting structure, separate from the enterprise ABS definition.

  1. Navigate to Projects > Alternate Structures.

  2. Click the Actions list and select Create Project ABS.

  3. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    The Project displayed in the green parameter bar at the top of the screen is the only project available for selection in the Create Project ABS dialog box.

  4. Click RUN and then OK.

    Only one project-specific ABS may be created per project.