Post Staging Actuals to Production - EcoSys - 2.03 - Help - Hexagon PPM

EcoSys Help - Projects (2.03)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
2.03

After staging actuals have been verified, this procedure allows you post them to production. This involves moving the staging actuals to production and deleting them from staging. Once the staging actuals are posted to production, a log entry appears in the Log tab.

Any staging actuals associated with a closed period will remain in staging.

  1. Navigate to Progress > Actuals.

  2. Click the Actions list and select Post Staging Actuals to Production.

  3. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    The Project displayed in the green parameter bar at the top of the screen is the only project available for selection in the Post Staging Actuals to Production dialog box.

  4. (Optional) Type in the Comment.

  5. Click RUN and then OK.