The time-phase settings defined (Start Date, End Date, or Curve) for each line item in the Original Budget screen (Budgets > Original Budget > Time-phasing tab) appear in the Forecast tab.
If Time-Phase Settings adjustment or balance method is assigned, then do not select Time-Phasing Method as Manual for that cost control object.
Follow the procedure below to update the existing time-phasing settings.
-
Navigate to Forecasts > Forecast.
-
Click the Time-phasing tab.
-
Click the Time-Phasing Method ellipsis to select the required time-phasing method. The available time-phasing methods are listed below:
-
BCK - Back-Loaded
-
BEL – Bell Curve
-
FRN - Front-Loaded
-
LIN – Linear
-
MAN- Manual
-
-
Select the required Start Date and End Date.
-
Click the Save icon.