Validate the New EAC - EcoSys - 2.03 - Help - Hexagon PPM

EcoSys Help - Projects (2.03)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
2.03

Once the forecast method and associated attributes have been updated, this procedure allows you to view and validate the updated Estimate at Complete (EAC). To understand the EAC, view the current forecast, current budget, and actuals line items.

  1. Navigate to Forecasts > Multi Project Forecast.

  2. Click the Current Forecast hyperlink for the selected project. The current forecast line items appear in the Current Forecast Details panel.

  3. Click the Current Budget hyperlink for the selected project. The current budget line items appear in the Current Budget Details panel.

  4. Click the Actuals hyperlink for the selected project. The actuals line items appear in the Actual Cost Details panel.

    Reviewing actuals allows you to identify unexpected actuals established for the selected cost control objects.