This procedure allows you to re-open a previously approved change, including the removal of all applicable data from the Current Budget and Current Forecast. Once a change is reopened, a log entry appears on the Log tab and the status of the change updates to Open. A re-opened change request may be updated. The project change creator, all users on the Change Workflow or All Workflows - Distribution List for budget, scope and forecast.
Changes approved during or prior to the project period of the most recent forecast variance change cannot be re-opened.
-
Navigate to Changes > Changes.
-
Click the Actions list and select Re-Open Change.
-
Click the Project ellipsis to select required project.
The Project displayed in the toolbar at the top of the screen is the only project available for selection in the Re-Open Change dialog box.
-
Click the Change ellipsis to select required change.
-
(Optional) Type a Comment.
-
Click RUN.