Current Budget - EcoSys - 4.11 - Help - Hexagon

EcoSys Projects Help (4.11)

Language
English
Product
EcoSys
Subproduct
Project
Search by Category
Help
EcoSys Standard Version
4.11

The EcoSys Project’s Current Budget screen is used to view the current budget, which is composed of the original budget plus any approved changes. If the project is not time-phased (Time-Phase is not checked in the Projects > Project SetupGeneral tab), the current budget time-phased data will not be available.