This process allows you to import the external baseline according to the selected schedule EV basis.

  1. Click the Actions list and select Import External Project Baseline/Planned Value.

  2. Click the Project ellipsis and select the project for which you want to import the external baseline or planned value.

  3. Type the Comment related to importing external baseline or planned value.

  4. Click RUN.