To view the Project Performance EV (Cost) by Minor Periods report, perform any of the following actions.

  • View the report in the Earned Value screen:

    1. Navigate to Progress > Earned Value.

    2. Click the Reports tab.

    3. Click the Project Performance EV (Cost) by Minor Periods tab.

    4. Click the ellipsis for each of the below parameters and select the required values

      1. Click the Project ellipses and select the required project. By default, the last selected project appears.

      2. Click the Project Period ellipses and select the project period.

    5. Click the Run icon. The Project Performance EV Cost by Minor Periods report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Earned Value > Project Performance EV (Cost) by Minor Periods.

    2. Click the ellipsis for each of the below parameters and select the required values

      1. Click the Project ellipses and select the required project. By default, the last selected project appears.

      2. Click the Project Period ellipses and select the project period.

    3. Click the Run icon. The Project Performance EV (Cost) by Minor Periods report appears.