After staging actuals have been verified, this procedure allows you post them to production. This involves moving the staging actuals to production and deleting them from staging. Once the staging actuals are posted to production, a log entry appears in the LOG tab.

  • The Staging Actuals of the Project Path IDs which are not set to CCL, will not be posted to Production.

  • Any staging actuals associated with a closed period will remain in staging.

  1. Navigate to Progress > Actuals.

  2. Click the Actions list and select Post Staging Actuals to Production.

  3. Click the Project ellipsis and select the required project. By default, the last selected project appears.

    The Project displayed in the toolbar at the top of the screen is the only project available for selection in the Post Staging Actuals to Production dialog.

  4. (Optional) Type the Comment.

  5. Click RUN.