A defined set of time-phase methods can be used to establish the Curve, Start Date, and End Date. Once established, these attributes will be utilized when time-phasing the estimate project. The following time-phasing methods can be assigned:
-
Back Loaded: Line items spread in a back-loaded curve.
-
Front Loaded: Line items spread in a front-loaded curve.
-
Linear: Line items spread linearly.
-
Bell: Line items spread in a bell curve.
-
Navigate to Estimating > Estimate Summary.
-
At the top of the screen, in the green parameter bar, click the Project ellipsis to view all the estimate details.
-
Click Refresh for screen update.