All Original Budget time-phased results may be viewed on the Time-Phasing tab, regardless of budget status.

The Delta Cost field can be used to easily view variances at the object level caused by discrepancies between the total amounts (costs, hours, and quantities) and time-phased amounts.

If the Delta Cost has a green background, the object’s Total Cost, Total Quantity, and Total Hours equals the total time-phased values. If the Delta Cost field has a red background, the object’s Total Cost does not equal the time-phased cost. If the Delta Cost field has a yellow background, the object’s Total Hours or Total Quantity do not equal the time-phased hours or quantity.

Follow the procedure below to review results of either manual or systematic time-phasing.

  1. Click the Time-Phasing tab.

  2. In the Original Budget Time-Phasing panel, click the Time-Phased Cost hyperlink of the object. The time-phasing details of the selected objects appears in the Time-Phasing Manual Details panel.

    SHARED Tip If a parent object is selected, budget details for all the object’s children will be displayed.