This procedure allows you to update the adjustment methods in the Forecast Balance and Adjustment dialog box in the Forecast Time-Phasing panel.

If Time-Phase Settings adjustment method is assigned, then do not select Time-Phasing Method as Manual for that cost control object.

  1. Navigate to Forecasts > Forecast.

  2. Click the Time-phasing tab.

  3. Click the New EAC hyperlink for a required cost control object.

    1. For CCL objects:

      1. Click the Forecast Adjustment Method ellipsis and select the required adjustment method. The available adjustment methods are listed below:

        Adjustment to Time-Phasing End

        Adjustment to Next

        Adjustment to Future Periods

        Adjustment to Year End

      2. Type the number of Adjustment Periods for the cost control object with Adjustment to Future Periods adjustment method.

      3. Click SAVE. The Adjustment ETC End Date gets updated.

      4. Click the Refresh Forecast Adjustment hyperlink and then click OK.

        The bar chart is updated and displays the adjustment amount distributed as per the adjustment method selected.

    2. For Non-CCL objects, click Refresh Forecast Adjustment hyperlink and then click OK.

      The bar chart gets updated and adjusts all the children of WBS.