Progress methods can be manually established in the Earned Value Summary panel. If the Progress Method is Physical % Complete, the Physical % Complete column will become unprotected and available for editing as indicated by the yellow fill. Preview % Complete will be displayed for all progress methods, except for Apportioned Effort. This field is calculated when the screen is refreshed and may be used to view the percent complete that will be generated when the Generate Earned Value action is run.

  1. Navigate to Progress > Earned Value.

  2. In the Project Navigation Register panel, do the following:

    1. (Optional) In the green parameter bar, click the Project Controller ellipsis to select the project controller.

      All the projects that are controlled by the selected project controller are displayed.

    2. (Optional) In the green parameter bar, click the Project Manager ellipsis to select the project manager of the project.

    3. (Optional) In the green parameter bar, click the Portfolio ellipsis to select the portfolio to which the project belongs to.

    4. Select the required project row to view and edit its project details.

      The project details are displayed on the right-hand side.

      (Or)

      On the right-hand side, at the top of the screen, in the green parameter bar, click the Project ellipsis to select the required project.

  3. At the top of the screen, in the green parameter bar, click the Project Period ellipsis to select the required project period.

  4. If required, click REFRESH to update the screen.

  5. Click the Earned Value tab.

  6. Click the Progress Method ellipsis to select the required progress method. The available progress methods are listed below.

    • Apportioned Effort

    • Contract VOWD

    • Earn as Actual

    • Earn as Planned

    • Fixed Formula 0/100

    • Fixed Formula 0/50/100

    • Hours % Complete

    • Physical % Complete

    • Progress Package

    • S3D Progress

    • Schedule % Complete

    • Schedule Activity % Complete

    • Schedule Cost % Complete

    • Schedule Hours % Complete

    • SMART Build

    • Weighted Deliverables

    • Weighted Milestone

    • Weighted Quantities

  7. Click the Save icon.