This procedure allows you to view and update the general schedule details of each activity.

  1. In the Activity Scheduler panel, select the activity row for which you want to update general attributes.

  2. In the Activity Task Scheduler Tabs panel, click the General tab.

  3. Type in the required Activity ID and Activity Name.

  4. Type the number of hours/days required for the activity in the Original Duration field.

  5. Select the units from the Duration Units list.

  6. Type in the Objective of the activity.

  7. Click the Activity Calendar ellipsis and select the calendar for the activity.

    External fields will be populated by the P6 Integration.