Create Project Schedule Activity Structure - EcoSys - 4.01 - Help - Hexagon PPM

EcoSys Projects Help (4.01)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
4.01

This procedure allows you to view or create a project schedule structure for a project.

  1. Click the Project Structure tab and then Project Structure Register tab.

  2. Right-click the rows list and select Insert Under. This creates a new row under the selected line item.

    Do not choose Insert or Insert Multiple options. If these options are used, the project structure will not be added as a part of the project unless the parent path ID is also specified.

    • The Insert Under option places the project structure below the selected line item.

    • If the Insert Row option is used, the project structure is placed at the same hierarchy as the selected line item.

  3. Type in a unique ID and Name for the project object.

  4. Click the ellipsis for each of the below fields and select the required values.

    • Type - Select the project object type.

    • Parent Path ID - Select the required parent.

      If you do not select parent path ID, EcoSys automatically selects the immediate parent available in the project structure after saving.

    • Cost Control Level - To be able to define the project cost for the project structure, set the cost control level to Yes.

    • ICMS Cost Categories and Groups - Select the project object category.

    • Calendar - Select the required calendar.

  5. Click the Save icon.

    • Click the Delete Row(s) icon to delete the selected row.

    • You can customize the view of the Maintain Project Structure spreadsheet from the view settings.