  1. In the Tree view, select the node where the copy of the drawing will reside.

  2. In the List view, select the location where you want to paste the copy of the drawing.

  3. Click Paste on the main toolbar.  The software displays the Transformation Programs dialog box.

    The options that appear on the Transformation Programs dialog box depend on the transformation program defined by the Options Manager setting Copy Transformation Program.  You can copy the delivered code and then create your own customized transformation program.  The delivered transformation program used for copying drawings is CopyTransformation.Transform.

  4. Click the Generate new sequence numbers option if you would like new sequence numbers to be created.  Selecting the option causes existing tag sequence numbers to be set to null for any item that has the property TagSequenceNo.  The null sequence number triggers the creation of new sequence numbers during normal item tag validation. An exception to this is that the tag sequence number for an instrument item is not set to null.  Item tag validation does not generate a new sequence number for an instrument. Instrument tags will be duplicated at the target.

  5. Click to select the Add value to the beginning of all sequence numbers to use this option.  Click in the provided field and enter the values you want to display at the beginning of all your sequence numbers.

  6. Click to select Keep exiting if unique to use this option.

  7. Select the Clear piping material classification check box to remove any defined piping materials class.

  8. Select the Clear process data check box to remove any values in the Process category.

  9. Click OK.  The software displays the Paste Drawings dialog box.

  10. When the processes are complete, click View Log to view the report or click Close to dismiss the Paste Drawings dialog box.

  • You must have the appropriate permissions, specified in SmartPlant Engineering Manager, in order to paste drawings.

  • For more information about creating a transformation program, see Customizing the Sample Projects in the SmartPlant P&ID Programmer's Guide.